China CAMC Engineering Co., Ltd.-constructed (CAMCE) Ishiara switch station, Sotik switch station and Bomet substation of the Kenya Power Transmission System Improvement Project (Lot 3A & Lot 3B) have been awarded running acceptance certificates recently.
By Dec. 21, 2016, the project has been taken over by its employer, helping CAMCE win reputation in Kenya and laying sound foundation for the Chinese power project engineering firm’s sustained development in the country.
Previously on Dec. 31, 2015, CAMCE completed all improvement work related to the Kenya Power Transmission System Improvement Project (Lot 3A & Lot 3B) and received the certificate of completion from the project’s consultant firm - SMEC International Pty Limited.
(Source: China CAMC Engineering Co., Ltd.)