Photo shows the construction site of the 500-KV substation built by the State Grid Hunan Electric Power Transmission & Transformation Co., Ltd.
CHANGSHA, Oct. 1(Xinhua) -- Construction of a 500-KV substation in central China's Hunan Province was on full swing on China's National Day, which falls on Oct. 1, as workers were conducting final adjustment of a 35-KV equipment.
Photo shows the power grids in central China's Hunan Province.
According to Peng Xinlin, project manager of the State Grid Hunan Electric Power Transmission & Transformation Co., Ltd., the construction team worked around the clock and overcame bad weather condition to make sure that the project could be finished on time.
As the first 500-KV substation in western Hunan, it is expected to put in use on October 13. Upon completion, the substation will optimize the 220-KV power grid structure and transmit clean energy such as hydro-power and wind power, advancing Hunan's west-to-east power transmission and guaranteeing the province's power supply.
Photo shows staff member works at the construction site of the State Grid Hunan Electric Power Transmission & Transformation Co., Ltd. during National Day holiday.
Aerial photo shows the construction site of the 500-KV substation in western Hunan.